Engineer-in-Chief (E-in-C) visited Jagran - II Hydropower Project on 17 November 2021. During the visit, he attended Break Through Ceremony of the Headrace Tunnel. Excavation of the tunnel was attempted simultaneously from both ends, meeting in the middle in just 485 working days. This feat has been achieved at JHPP-II with a tolerance of less than 2.5 centimeter. Previously, similar feat at the same project was achieved with 10-centimeter tolerance on 27 January 2021.

E-in-C was given detailed briefing about the project by Commander 491 EG and later shown works being execution at various components of the project. E-in-C appreciates the quality of work & standards being achieved by FWO workforce.