1.    Water supply project having 121 Km length incl 94 km canal, 18 km siphon & 773 Meter intake and 81x culverts.1.  Water supply project having 121 Km length incl 94 km canal, 18 km siphon & 773 Meter intake and 81x culverts.
2.   An alternative route & corridor to serve Karachi water needs for the next 50 yrs which will reduce the shortage of water in the area and can provide 1200 cusec (250 MGD) of water.
3.   A proper Scheme that passes through the most economical route with gravity requiring the least pumping and fulfills the needs of the area that is strategically away from the sea/existing system.
4.    Project has been divided into 6 x Sections (22 Km, 21.8 Km, 19 Km, 21.8 Km, 17.2 Km & 19 Km) for in-time completion.

 

Project Details

 Project Name: 

Greater Karachi Bulk Water supply scheme K-IV Phase-I (260 MGO) Pkg-A. Conveyance system

 Project Location within  Country: Kinjar Lake to Hub Canal Karachi-Thatta (Sindh)
Name of Client / Sponsor: Karachi water & Sew Board (KWSB)
 Consultant:  Osmani & Co (pvt) Ltd.
 Start Date (Month / Year): Jun 2018
     
 Country:  Pakistan
 Scope of Work:

121 Km  incl 99 Km canal,
 773 Meter intake structure 
81x Culverts, 
0.425 Meter Aqueduct, 
18 km Siphons.

 Name of Associated  Firm (s)  
 Total Project Cost:  Rs 15255 Mn
 Completion Date
Ju 2020